Indicators
Technical-economic indicators
-Investment completion period: 46 months, between 2011-2015, extended by phasing in 2016
-Total investment value (eligible costs): 110.875.965 euro
Physical indicators according to the Financing Contract
WATER SYSTEMS:
Indicators to achieve – Water supply |
Unit |
Length/Number (approximate value) |
Surface intake rehabilitation |
no. |
1 |
Water mains extension and rehabilitation |
Km |
106,01 |
Distribution network extension and rehabilitation |
Km |
56,30 |
New and rehabilitated pumping stations |
no. |
14 |
New and rehabilitated storage tanks |
no. |
5 |
Drinking water treatment plants (new and rehabilitated) |
no. |
6 |
WASTE WATER SYSTEMS:
Indicators to achieve – waste water |
Unit |
Length / Number (approximate value) |
Sewerage networks extension |
km |
74,92 |
Rehabilitated sewerage networks |
km |
7,39 |
Discharge pipes (new and rehabilitated) |
km |
7,5 |
New and rehabilitated waste water pumping stations |
no. |
30 |
New and rehabilitated waste water treatment plants |
no. |
5 |